It Takes 2 Hours Of Direct Labor To Produce A Carving Bartels Standard Labor Cos

It takes 2 hours of direct labor to produce a carving. Bartels” standard labor cost is $12 per hour. During August, Bartels produced 10,000 carvings and used 21,040 hours of direct labor at a total cost of $250,376. What is Bartels” labor rate variance for August? Bradford Company budgeted 4,000 pounds of material costing $5.00 per pound to produce 2,000 units. The company actually used 4,500 pounds that cost $5.10 per pound to produce 2,000 units. What is the direct materials quantity variance and the direct materials price variance?

"Order a similar paper and get 100% plagiarism free, professional written paper now!"

Order Now